Ahmedabad's Metro Rail Phase-1 project to be completed by August 2022

Image Source: Internet

Ahmedabad, India (Metro Rail Today): In its endeavor to complete the Ahmedabad Metro Rail Project Phase 1 by August 2022 so as to coincide with the 75th year of India’s independence, Gujarat metro rail corporation (GMRC) completed a milestone today by placing the OWG (Open Web Girder) spanning – 7 Railway tracks at Sabarmati. 

The Open Web Girder is 73m long and 12m wide. It is made of more than 550 MT steel members tied together by 18500 HSFG bolts. The total weight of the girder is 850 MT. The girder is launched using two winch machines and at a launching speed of 250mm per minute. 

Image Source: Internet

GMRCL has expressed special thanks to Indian railways for their continuous support in carrying out this complex work as well as to GoG, Collectorate Ahmedabad and AMC for their support in land acquisition.