Nagpur Metro has completed almost 75% of track laying on Reach II

Image Source: Maha Metro

 Mumbai, India (Metro Rail Today)
: The work on track laying on Reach II (Sitabuldi Interchange to Automotive Square) is progressing fast with around 75% of the work completed. The stretch will be completed in December end. 

The total length of the track, both up and down lines is 14,173 meters. Out of this 10,324 meters has been laid while 4,049 meter remains. In terms of kilometers Reach II is 7.1 km long of which work on 5.2 km is complete.

Reach II is an important stretch of Nagpur Metro. People living in North Nagpur will be able to use the metro when it becomes operational. The important localities catered to by this Reach are Kamptee Road, Gaddigodam, Kabdi Square, Indora, etc. It will provide connectivity to Zero Mile and Kasturchand Park. Feeder services will enable commuters to reach government offices in Civil Lines.

Maha Metro is creating huge commercial space at Zero Mile Free Freedom Park and Kasturchand Park stations. People will be able to reach the commercial establishments in these stations using the metro.


The Union Cabinet is expected to approve Phase II of Nagpur Metro in the coming days. Under Phase II, the Metro will be extended from Automotive Square to Kanhan (via Kamptee). Once this is complete, lakhs of people commuting to Nagpur from Kamptee and Kanhan will be able to do so in comfort using the metro.

Post a Comment

0 Comments